Despite the temperatures which are reaching 40C degrees, the works on the construction of the outside water fountain with a pawn in the Park “Ravne 2” are progressing without reducing intensity.
Almost the entire surface of the fountain is covered with the river stone. The contractors made four cascades which will benefit the faster and louder water flow.
The excavator started with digging the channel which will bring the water caught in the first valley. Here we have four small springs active throughout the year never drying out. During the winter season, when the fountain is out of function the water will be released in the existing springs.
In several days the exterior LED lights will be installed. It’s expected that the fountain will be operational at the planned time of ten days, or until August 21, 2017. The final works are related to the landscaping of the terrain around the fountain, planting of the bushes and mounting of the bridges over the cascades.